Tuesday, 14 June 2011
Page: 5966


Mr ROBERT (Fadden) (16:55): I have always wanted to ask you a question, Minister, regarding phase 1B of the AIR 7000 to see if you are across the 300 or 400 projects. Phase 1B is, of course, the multimission unmanned aerial vehicles, the strategic UAE capability. In 2006 the estimated year of decision for the unmanned aerials was 2007-08 and anticipated costs were $1 billion to $1.5 billion. The 2009 DCP now has the year of decision going out to 2019, a slippage of 11 years. Can the minister possibly explain the strategic rationale for a slippage of 11 years in terms of what is a high-end maritime surveillance capability?