Fast broadband on the way for Cowper

Download PDFDownload PDF

Luke Hartsuyker MP Minister for Vocational Education and Skills Federal Member for Cowper


Luke Hartsuyker’s Media Contact: Nikki Voss 02 6652 6233 / 0408 070 056

October 16, 2015

Fast broadband on the way for Cowper

NBN Co has announced the construction schedule for superfast broadband to roll out to more than 26,400 North Coast homes and businesses over the next three years.

The construction schedule released today outlines the plan to network 9.5 million premises nationwide over three years with work commencing in the Cowper electorate next year.

“Superfast broadband is vital for our North Coast regional businesses to flourish and grow,” Luke Hartsuyker said.

“The news that construction of fixed line broadband and fixed wireless internet will start in the third quarter of next year is positive for businesses and residents the length and breadth of the Cowper electorate.

“While I would like to see every residence and business connected to superfast broadband as soon as possible, as with any major infrastructure project, the simple reality is that is takes time.

“The Coalition’s accelerated construction program will bring NBN to the North Coast six years faster than if Labor was in Government.

“This plan demonstrates the Coalition’s commitment to rural and regional Australia in closing the digital divide by providing fast internet to every home and business by 2020.”

The new NBN rollout plan which continues to September 2018, provides a breakdown of when the network will be starting in specific locations across the North Coast and the type of technology that will be used.

“Internet access is vitally important for our North Coast communities; it transforms education, health care and other critical online services and boosts business competitiveness and growth potential,” Mr Hartsuyker said.

“Businesses will also benefit from the vastly higher bandwidth available.”

Nationwide, more than 1.3 million homes and businesses can now order an NBN service and there are almost 700,000 homes and business under construction. Around 600,000

premises already have an active connection and are enjoying the benefits of very fast broadband.

I will continue to keep North Coast residents informed of the progress of this important project for Australia.

Please find the attached construction timetable for the Cowper electorate:

H1 - First half of the year H2 - Second half of the year

Residents can check their suburb at:

Fixed Line Rollout Localities Approx.

Premises Construction begins

Mylestom, Raleigh, Repton, Urunga 1,800 Q1-2017

Bowraville, Hyland Park, Macksville, Nambucca Heads, North Macksville, Scotts Head, Valla Beach 6,900 Q1-2017

Dorrigo 400 H2-2017

Bellingen 1,400 H2-2017

Arakoon, South West Rocks 3,000 H1-2017

Aldavilla, East Kempsey, Greenhill, Kempsey, South Kempsey, West Kempsey, Yarravel 4,400 Q3-2016

Gulmarrad, Maclean, Townsend 2,300 H1-2018

Arrawarra, Arrawarra Headland, Corindi Beach, Emerald Beach, Moonee Beach, Mullaway, Safety Beach, Sandy Beach, Woolgoolga

6,200 H1-2017

Fixed Wireless Rollout Localities Approx.

Premises Construction begins

Gumma 160 Q3-2016

Barcoongere, Minnie Water 370 Q1-2017

Kempsey 170 Q3-2016

Mororo, Palmers Island 270 Q3-2016