Thursday, 3 July 1941


Senator McBRIDE - The answers to the honorable senator's questions are as follows : -

1.   The building has been completed and the electrical installation is proceeding. Approximately 50 per cent, of machine tools required have been delivered. Deliveries are continuing but installation of such tools has not yet commenced.

2.   It is anticipated that operations will commence about the end of August.

3.   The site has been selected and preliminary planning is under way. The plant has been ordered and is now being manufactured. The building operations will commence in about one month. It is contemplated that the factory should be completed, and commence production in about nine months' time.