Notice given 5 March 2012

1572  Senator Johnston: To ask the Minister representing the Minister for Defence—As at 31 December 2011, how many: (a) permanent uniformed staff, both part-time and full-time; and (b) civilian staff, both part-time and full-time, were in each of the service areas (i.e. army, navy, and air force).

 

 1573  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many uniformed full-time, permanent personnel were recruited to each of the service areas (i.e. army, navy and air force).

1574  Senator Johnston: To ask the Minister representing the Minister for Defence—

(1) For the period 1 January to 31 December 2011, how many: (a) uniformed staff; and (b) civilian staff, resigned from each of the service areas (i.e. army, navy and air force).

(2) For the period 1 January to 31 December 2011, how many: (a) uniformed staff; and (b) civilian staff, were made redundant or accepted severance packages in each of the service areas.

1575  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many temporary civilian positions, both full-time and part-time, were created in the department, in the Defence Materiel Organisation and in the Defence Science and Technology Organisation.

1576  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many temporary civilian positions, including part-time, existed in the department, in the Defence Materiel Organisation and in the Defence Science and Technology Organisation.

1577  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many civilian employees, including full-time and part-time, were employed on contract and at what levels of remuneration.

1578  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what was the average cost in recruiting each new uniformed person into each of the service areas (i.e. army, navy and air force).

1579  Senator Johnston: To ask the Minister representing the Minister for Defence—What was the total expenditure on recruiting for the period 1 July to 31 December 2011.

1580  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how much was paid to the Australian Defence Force prime recruiting agency for the provision of services.

1581  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what specific savings have been made in the Strategic Reform Program (SRP) ‘Provisional Savings and Costs - Gross SRP Stream Savings’ for: (a) information and communications technology; (b) inventory; (c) logistics; (d) non-equipment procurement; (e) Reserves; (f) shared services; and (g) workforce.

1582  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what specific savings have been made in the Strategic Reform Program (SRP) ‘Provisional Savings and Costs - SRP Stream Costs’ for: (a) information and communications technology; (b) inventory; (c) smart maintenance; (d) logistic; (e) non-equipment procurement; (f) preparedness and personnel and operating costs; (g) Reserves; (h) shared services; (i) workforce; and (j) Mortimer implementation.

 

 1583  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what specific savings have been made in the Strategic Reform Program (SRP) ‘Provisional Savings and Costs - SRP Stream Net Savings’ for: (a) information and communications technology; (b) inventory; (c) smart maintenance; (d) logistic; (e) non-equipment procurement; (f) preparedness and personnel and operating costs; (g) Reserves; (h) shared services; and (i) workforce.

1584  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what specific savings have been made in the Strategic Reform Program ‘Other Savings’ for the following areas: (a) zero based budgeting review; (b) minor capital program; (c) facilities program; (d) administrative; and (e) productivity.

1585  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications’:

(1) As at 31 December 2011, how many uniformed personnel, full-time and part-time, were employed.

(2) As at 1 July and 31 December 2011, how many uniformed personnel were employed on the projects.

1586  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Military Workforce’:

(1) As at 31 December 2011, how many civilian personnel, full-time and part-time, were employed in implementing the White Paper initiatives.

(2) As at 1 July and 31 December 2011: (a) how many civilian personnel were employed; and (b) in what programs.

1587  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Military Workforce’: For the period 1 July to 31 December 2011, how many uniformed personnel, including full-time and part-time, were employed in implementing the White Paper initiatives.

1588  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Military Workforce’: For the period 1 July to 31 December 2011, what reduction has there been in the number of personnel, including full-time and part-time, employed in implementing: (a) efficiency improvements; (b) civilianisation; and (c) support productivity improvements.

1589  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Military Workforce’: As at 31 December 2011, what increase or reduction has there been in civilian personnel employed, full-time and part-time, in the department and in the Defence Materiel Organisation since 1 July 2008.

1590  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Civilian Workforce’: For the period 1 July to 31 December 2011, how many personnel, including full-time and part-time, were employed as Australian Public Service staff or contractors.

 

 1591  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program (SRP) ‘Indicative Workforce Implications - Civilian Workforce’: For the period 1 July to 31 December 2011, how many Australian Public Service staff or contractors, including full-time and part-time, were employed on White Paper/SRP initiatives.

1592  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Civilian Workforce’: For the period 1 July to 31 December 2011, what reduction has there been in the number of Australian Public Service staff or contractors employed in implementing: (a) efficiency improvements; (b) civilianisation; (c) support productivity improvements; and (d) contractor conversion (reduction to contractors).

1593  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the White Paper and the Strategic Reform Program ‘Indicative Workforce Implications - Civilian Workforce’: As at 31 December 2011, what increase or reduction has there been in full-time and part-time Australian Public Service staff or contractors employed since 1 July 2008.

1594  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011:

(1) Which submarines in the Royal Australian Navy fleet were fully operational ready for tasking with a full crew complement and capable of completing Unit Ready Days and Tasking Ready Days.

(2) How many actual sea going fully operational days were achieved by each submarine.

1595  Senator Johnston: To ask the Minister representing the Minister for Defence—

(1) For the period 1 July to 31 December 2011: (a) which submarines in the Royal Australian Navy (RAN) fleet were non-operational; and (b) for each submarine that was non-operational, what was the reason for its non-operational status.

(2) For the period 1 July to 31 December 2011, which submarines in the RAN fleet were: (a) fully operational and ready to respond to ‘war like’ situations; and (b) for what periods.

(3) What was the cost of maintaining the six submarines for the periods: (a) 1 July to 31 December 2011; and (b) 1 January to 31 December 2011.

(4) What was the total cost of operating the six submarines for the periods: (a) 1 July to 31 December 2011; and (b) 1 January to 31 December 2011.

(5) What was the total cost of upgrading the six submarines for the periods: (a) 1 July to 31 December 2011; and (b) 1 January to 31 December 2011.

(6) What were the crewing complements for each of the six submarines for each month in the periods: (a) 1 July to 31 December 2011; and (b) 1 January to 31 December 2011.

1596  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) how many fully qualified personnel are ‘Dolphin Qualified’ and permanently employed in the Royal Australian Navy to operate submarines; and (b) how many ‘Dolphin Qualified’ personnel were tasked with other duties and what were these duties.

 

 1597  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many personnel fully completed training courses and became ‘Dolphin Qualified’ and eligible to serve on submarines.

1598  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, how many personnel completed training courses and became ‘Perisher Qualified’ and eligible to command a submarine.

1599  Senator Johnston: To ask the Minister representing the Minister for Defence—As at 31 December 2011, how many Royal Australian Navy personnel were ‘Perisher Qualified’ and eligible to command a submarine.

1600  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, which submarines were undergoing maintenance/refit programs and for what length of time.

1601  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011:

(1) Which naval vessels were fully operational with a full crew complement.

(2) Which naval vessels were not fully operationally ready for immediate tasking.

(3) For each naval vessel that was non-operationally ready, what was the reason for its non-operational status.

(4) What were the operational strengths on all naval vessels of the: (a) engineering officers and sailors; and (b) non-engineering officers and sailors.

1602  Senator Johnston: To ask the Minister representing the Minister for Defence—Given that video communications are integrated into robots, soldiers and unmanned aerial vehicles, and network-centric warfare is becoming the organising principle of war fighting, and frontline demands for bandwidth are rising at a rapid rate: For the period 1 July to 31 December 2011, what did the Australian Defence Force do and how much did it spend on: (a) establishing a network-centric warfare capability; and (b) addressing the issue of increased bandwidth.

Senator Johnston: To ask the Ministers listed below (Question Nos 1603-1605)—

(1) For the period 1 July to 31 December 2011, for each agency within the responsibility of the Minister, how much was spent on media monitoring.

(2) As at 1 July and 31 December 2011: (a) how many staff, uniformed and civilian, full-time and part-time, were employed in public relations and/or the media in the department or each agency within the responsibility of the Minister; (b) what were the position levels of these staff; and (c) how many of these staff were: (i) permanent, (ii) temporary, or (iii) contractors.

1603 Minister representing the Minister for Defence

1604 Minister representing the Minister for Defence Materiel

1605 Minister representing the Minister for Defence Science and Personnel

Senator Johnston: To ask the Ministers listed below (Question Nos 1606-1608)—For the period 1 July to 31 December 2011, for each agency within the responsibility of the Minister/Parliamentary Secretary: (a) what communications programs were undertaken or were planned to be undertaken; and (b) what was the total spend in each communications program.

 

 1606 Minister representing the Minister for Defence

1607 Minister representing the Minister for Defence Materiel

1608 Minister representing the Minister for Defence Science and Personnel

Senator Johnston: To ask the Ministers listed below (Question Nos 1609-1611)—

(1) For the period 1 July to 31 December 2011: (a) what was the hospitality spend for each agency within the responsibility of the Minister/Parliamentary Secretary; and (b) for each hospitality event, can the following details be provided: (i) the date, (ii) the location, (iii) the purpose, (iv) the cost, and (v) the number of attendees.

(2) For the period 1 July to 31 December 2011, can details be provided of the total hospitality spend for the office of the Minister/Parliamentary Secretary.

1609 Minister representing the Minister for Defence

1610 Minister representing the Minister for Defence Materiel

1611 Minister representing the Minister for Defence Science and Personnel

Senator Johnston: To ask the Ministers listed below (Question Nos 1612-1614)—For the period 1 July to 31 December 2011:

(1) (a) Did the Minister/Parliamentary Secretary travel overseas on official business; if so: (i) to what destination, (ii) for what duration, and (iii) for what purpose; and (b) what was the total cost of: (i) travel, (ii) accommodation, and (iii) any other expenses.

(2) (a) Which departmental and uniformed personnel accompanied the Minister/Parliamentary Secretary on each trip; and (b) for those personnel, what was the total cost of: (i) travel, (ii) accommodation, and (iii) any other expenses.

(3) (a) Apart from ministerial staff and uniformed and civilian departmental personnel, who else accompanied the Minister/Parliamentary Secretary on each trip; and (b) for each of these people, what was the total cost of: (i) travel, (ii) accommodation, and (iii) any other expenses.

1612 Minister representing the Minister for Defence

1613 Minister representing the Minister for Defence Materiel

1614 Minister representing the Minister for Defence Science and Personnel

Senator Johnston: To ask the Ministers listed below (Question Nos 1615-1617)—For the period 1 July to 31 December 2011, in regard to the department and each agency within the responsibility of the Minister/Parliamentary Secretary:

(1) How many freedom of information (FOI) requests were received.

(2) How many FOI requests were granted or denied.

(3) How many conclusive certificates were issued in relation to FOI requests.

1615 Minister representing the Minister for Defence

1616 Minister representing the Minister for Defence Materiel

1617 Minister representing the Minister for Defence Science and Personnel

Senator Johnston: To ask the Ministers listed below (Question Nos 1618-1620)—For each portfolio/agency within the responsibility of the Minister/Parliamentary Secretary:

(1) How many reviews are currently being undertaken in the portfolio/agency or affecting the portfolio/agency.

 

 (2) What was the commencement date of each review.

(3) When will each review conclude.

(4) (a) Which reviews were completed in the period 1 July to 31 December 2011; and (b) when will the Government respond to the each of these reviews.

(5) As at 31 December 2011, what was the cost of each of these reviews.

1618 Minister representing the Minister for Defence

1619 Minister representing the Minister for Defence Materiel

1620 Minister representing the Minister for Defence Science and Personnel

1621  Senator Johnston: To ask the Minister representing the Minister for Defence—As at 31 December 2011:

(1) With reference to the acquisition of the first 2 F-35 Joint Strike Fighter (JSF) aircraft: (a) what is the expected expenditure on the acquisition; and (b) what is to be supplied as equipment, supporting systems, weapons, services or infrastructure to the Australian Defence Force (ADF).

(2) With reference to the acquisition of a further 12  F-35 JSF aircraft: (a) what is the expected expenditure on the acquisition; and (b) what is to be supplied as equipment, supporting systems, weapons, services or infrastructure to the ADF.

(3) When will these first 14 F-35 JSF aircraft: (a) be delivered; (b) become fully operational; and (c) what is the estimated through-life support and operating costs for these aircraft over an expected 30 year period of operation.

(4) When will the remaining 86 F-35 JSF be purchased (as referenced in the Defence White Paper 2009 , p. 78, paragraph 9.60, ‘The Government has decided that it will acquire around 100 F-35 JSF, along with supporting systems and weapons. The first stage of this acquisition will acquire three operational squadrons comprising not fewer than 72 aircraft’).

(5) With reference to the acquisition of the remaining 86 F-35 JSF aircraft: (a) what is the expected expenditure on the acquisition; (b) what will be supplied as equipment, supporting systems, weapons, services or infrastructure to the ADF; (c) when will the aircraft be delivered; (d) when will they become fully operational; (e) where will the JSF squadrons be based, and when; and (e) what is the estimated through-life support and operating costs over an expected 30 year period of operation.

(6) What savings would be made by cancelling the purchase of 24 F-35 JSF aircraft and purchasing 24 Super Hornets.

1622  Senator Johnston: To ask the Minister representing the Minister for Defence—As at 31 December 2011:

(1) Is it still planned to acquire 12 submarines as per the White Paper direction ‘the Government takes the view that our future strategic circumstances necessitate a substantially expanded submarine fleet of 12 boats in order to sustain a force at sea’ ( Defence White Paper 2009 , p. 64, paragraph 8.40).

(2) What plans and strategies are in place to man the 12 future submarines given the great difficulty, in 2010-11, of manning and operating the current fleet of submarines.

 

 (3) What is the expected cost of acquiring 12 future submarines, over the next: (a) 12 months; (b) 5 years; (c) 10 years; and (d) 15 years.

(4) What funding has been provided to assist in the planning for the 12 future submarines.

(5) When is it expected that the first pass approval will be provided to advance the purchase of the 12 future submarines.

(6) What are the expected through-life support and operating costs of a fleet of 12 future submarines over a 30 year operating period.

(7) When is it envisaged that the first of the 12 future submarines will be launched and fully operational.

(8) What is the expected cost per year of maintaining and operating the existing 6 Collins Class submarines until they are de-commissioned, broken down by year until 2025.

(9) What is the specific phasing-out program for the existing Collins Class submarines.

(10) What are the projected costs and project time-lines of the Submarine Lifetime Extension Program.

1623  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the Government commissioned report, 2008 Audit of the Defence Budget which identified that ‘a real growth rate of 3.5% in capital expenditure on SME [Specialised Military Equipment] [is required] just to replace today’s equipment. To deliver the capabilities proposed in the recommended Force Structure Option requires a growth rate of 4.2%’: As at 31 December 2011, what will be the amount required to fund, in nominal dollars, the major capital equipment program each year from 2010-11 to 2029-30, so as to fund the White Paper ‘Force 2030’ initiatives.

1624  Senator Johnston: To ask the Minister representing the Minister for Defence—With reference to the Strategic Reform Program (SRP):

(1) For the period 1 July to 31 December 2011: (a) where specifically have the provisional savings of the forecasted total been made under the SRP; (b) can a detailed explanation be provided of where these savings have been realised; and (c) what one-off savings been made.

 (2) For the period 1 July 2008 to 31 December 2011, what workforce savings, both in personnel reductions and dollar savings, per area as specified in the Budget Audit Review, have resulted where the gaps to average performance have been: (a) improved and realized; and (b) reduced to zero.

1625  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011, what productivity improvement savings have been made by the department and by the Defence Materiel Organisation.

1626  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) what savings have been made in reducing the cost of combat capability through the use of Reserves and deployable contractors; and (b) have any one-off savings been made; if so, where were these savings found.

 

 1627  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) what specific productivity improvement savings have been made in Smart Sustainment reform; and (b) what one-off savings been made.

1628  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) what specific savings over the period 2010 to 2019 have been made in the implementation of Smart Maintenance techniques; and (b) what one-off savings been made.

1629  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) of the savings expected over the period 2010 to 2019, what specific savings have been made in the optimising of inventory holdings and the introduction of more efficient management techniques; and (b) what one-off savings been made.

1630  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) of the savings expected over the period 2010 to 2019, what specific savings have been made in Storage and Distribution (Logistics) Reform where the adoption of automated technologies and improved business practices ensure cost effectiveness and efficiency; and (b) what one-off savings been made.

1631  Senator Johnston: To ask the Minister representing the Minister for Defence—As at 31 December 2011:

(1) From which areas of expenditure will the enhanced force protection measures be made.

(2) What specific programs will be cut or deferred to meet this cost.

(3) Why did the Government cease disclosing deferrals in expenditure in the 2008-09 Budget which has continued through to the 2011-12 Budget.

(4) (a) What are the specific deferrals in expenditure since 2008-09; and (b) why have these deferrals been made.

(5) What percentage increase, if any, will be made to enable future capital equipment initiatives over the forward estimates period.

(6) As it is not clear in the 2011-12 Budget, what specific projects are planned for approval in 2011-12.

(7) (a) What programs in 2011-12 will now have to be resourced through absorbed costs; and (b) what programs have been cancelled or deferred to enable these costs to be absorbed.

(8) Of the $20.6 billion worth of savings under the Strategic Reform Program (SRP) it would appear that $4.6 billion of this involves the re-allocation of funds and is not a savings item at all - how can this claim of savings be made when it is in fact a reallocation of funds.

(9) Under the SRP: (a) why has the number of civilian employees to be cut been reduced from the forecast 3 125; and (b) what is the new figure.

1632  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011: (a) what ‘First Pass’ Project approvals; and (b) what ‘Second Pass’ Project approvals, have been made.

 

 1633  Senator Johnston: To ask the Minister representing the Minister for Defence—For the period 1 July to 31 December 2011:

(1) (a) How many training days have been allocated to Reserves in each state and territory; and (b) what is the budget allocation to provide these training days.

(2) (a) How many training days were actually used by Reserves in each state and territory; and (b) what was the actual expenditure to provide these training days.

1634  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Tactical Information Exchange Domain JP 2089, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1635  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Active Missile Decoy (AMD) SEA 1229 Phase 1, 2 and 3, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

 

 (j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1636  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Anzac Ships SEA 1348 Phase 2, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1637  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Anzac Ship Project - Underwater and Surface War Fighting Upgrade Pgm SEA 1348 Phase 3, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1638  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Guided Missile Frigate Upgrade Implementation SEA 1390 Phase 2.1, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1639  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Standard Missile Replacement SEA 1390 Phase 4, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1640  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project NULKA SEA 1397, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1641  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project FLIR and ESM for S-70B-2 Helicopters SEA 1405, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1642  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Evolved SEASPARROW SEA 1428, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1643  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Replacement Heavyweight Torpedo SEA 1429, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1644  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project COLLINS Class Replacement Combat System SEA 1439 Phase 4A, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

 

 (d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1645  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Maritime Communications Modernisation SEA 1442, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1646  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Armidale Class Patrol Boat Project SEA 1444, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

 

 (j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1647  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project ANZAC Anti-Ship Missile Defence SEA 1448, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1648  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Replacement of Afloat Support Capability SEA 1654, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1649  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Air Warfare Destroyer SEA 4000, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1650  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Airborne Early Warning and Control Aircraft AIR 5077, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1651  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project New Air Defence Command and Control Systems for Control Units 2 and 3 AIR 5333, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

 

 (e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1652  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Bridging Air Combat Capability AIR 5349 Phase 2, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1653  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Bridging Air Combat Capability AIR 5349 Phase 1, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

 

 (j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1654  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project F/A-18 Hornet Upgrade AIR 5376, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1655  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Air to Air Refuelling Capability AIR 5402, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1656  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Project Echidna Electronic Warfare Self Protection for ADF Aircraft AIR 5416, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1657  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Follow-on Standoff Weapon AIR 5418, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1658  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Joint Strike Fighter Aircraft AIR 6000, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

 

 (f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1659  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project AIR 7000: Phase 1B and 2B AIR 7000, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1660  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project C-17 Globemaster III AIR 8000, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1661  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Armed Reconnaissance Helicopter AIR 87, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1662  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Multi Role Helicopter AIR 9000 Phase 2, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1663  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project MH-60R Seahawk Romeo AIR 9000 Phase 8, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1664  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Airborne Surveillance for Land Operations JP 129, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1665  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Establishment of Special Operations Command JP 199, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

 

 (f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1666  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Next Generation Satellite Communications System JP 2008 Phase 4, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1667  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Ultra High Frequency Satellite Communications JP 2008 Phase 5A, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1668  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project ADF SATCOM Capability Terrestrial Upgrade JP 2008 Phase 3F, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1669  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Jindalee Operational Radar Network (JORN) JP 2025, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1670  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Joint Command Support Environment (JCSE) JP 2030 Phase 8, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1671  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project High Frequency Modernisation JP 2043, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1672  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Amphibious Watercraft Replacement JP 2048 Phase 3, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

 

 (f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1673  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Amphibious Deployment and Sustainment JP 2048 Phase 4 A/B, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1674  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Bulk Liquid Distribution JP 2059, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1675  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Geospatial Information Infrastructure and Services (GII&S) JP 2064 Phase 2, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1676  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Lightweight Torpedo Replacement Phase 3 JP 2070, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1677  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Lightweight Torpedo Replacement Phase 2 JP 2070, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

 

 (b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1678  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Battlespace Communications Systems (LAND) JP 2072, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1679  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Logistics for the Warfighter JP 2077, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

 

 (f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1680  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project ADF Deployable Logistics Systems JP 2077 Phase 2B.2, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1681  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Mulwala Redevelopment Project JP 2086, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

 

 1682  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Air Defence Target System JP 66 Phase 1, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1683  Senator Johnston: To ask the Minister representing the Minister for Defence Materiel—With reference to the major project Establishment of Tactical Assault Group (East) JP 2088 Phase 1, can the following details be provided:

(a) the date that the project was first proposed to Government as a major capital equipment initiative;

(b) the date of the first estimated date, time period, for first pass approval, as per the Defence Capability Plan (DCP), or when it was first proposed to Government;

(c) the date of the first estimated date, time period, for second pass approval, as per the DCP, or when it was first proposed to Government;

(d) the date of first pass approval;

(e) the date of second pass approval;

(f) the estimated acquisition cost when first proposed to Government;

(g) the amount spent to date on this project;

(h) the current estimated acquisition cost;

(i) the date of estimated initial operational capability when first proposed to Government;

(j) the current date of estimated initial operational capability; and

(k) the reason(s) for the delay in this project, if applicable.

1684  Senator Humphries: To ask the Minister representing the Minister for Defence Materiel—With reference to defective parade boots within the Australian Defence Force:

(1) What was the nature of the defect.

(2) When were the defective parade boots first issued.

 

 (3) How many pairs of the defective boots were: (a) issued; and (b) subsequently recovered.

(4) How many Reports on Defective or Unsatisfactory Materiel (RODUMs) were submitted in regard to the potential defect.

(5) How long did it take, from the time that the first report was lodged, until a replacement directive was issued.

(6) What action was taken to ensure all defective boots were removed from service.

(7) What was the cost incurred by the Commonwealth to replace the boots.

(8) Was any of this cost transferred to the boot manufacturer.

(9) Is the manufacturer still contracted by the department.

1685  Senator Humphries: To ask the Minister representing the Minister for Defence—With reference to Landing Helicopter Dock (LHD) ships and personnel development:

(1) What is the proposed posted strength of the LHD.

(2) What is the breakdown of personnel posted to the LHD in each of the service areas (ie. army, navy and airforce).

(3) What will the ORBAT be, including the: (a) size; (b) nature; (c) Corps, Category or Mustering; and (d) ranks.

(4) Can details be provided of how the members will be stationed aboard, including: (a) if it will be a posting or short-term secondment; and (b) the length of time.

(5) Which service area will have command over personnel.

(6) What allowances will be paid to members on board.

(7) Does the department currently have technically proficient personnel for each component of the LHD, in particular, for high voltage ancillaries.

(8) What tri-service training has been conducted to prepare members for employment aboard the LHD.

(9) Where will members be sourced from, for example, from a single brigade, ship or group.

(10) Has a tri-service training continuum been developed.